Program Tasks

The program is divided into 4 tasks:

Task 1 - Physics of Failure Methodology

Task 2 - Life Cycle Cost Prediction

Task 3 - Prototype Implementation

Task 4 - Full Scale Implementation Planning and Metrics Program Management

The PASES program utilizes several CALCE projects. Outline descriptions of these projects can be found on the CALCE website. Follow this link

The approach taken by the PASES program is illustrated in this figure

Program Deliverables

 
Deliverable Description Month Due Date Due
1) Interim life cycle cost prediction demonstration 21 February 2001
2) Annual technical reports
First year (including year 1 Milestones)
Second year
Third year

13
25
37

June 2000
June 2001
June 2002
3) Prototype implementation vehicle test plans 31 December 2001
4) Cycle time reduction and failure prevention methodology report 35 April 2002
5) Life cycle economic impact report 35 April 2002
6) Virtual qualification software 42 November 2002
7) Enhanced PRICE H/HL Software 42 November 2002
8) Program final report draft 47 April 2003
9) Full scale implementation plan 49 June 2003
10) Benefit metrics 49 June 2003
11) Program final report 51 August 2003
 

 

The project schedule is shown below: